Improvements in Chamblee and Doraville
Current and Future Capital Improvements
Information was last updated on March 2022.
The CID makes no claims as to the accuracy of this information.
CID Projects
Peachtree Boulevard Gateway Improvements
Intersection realignment at the intersection of Peachtree Boulevard at North Shallowford Road and Peachtree Road
- Phase: Preliminary Engineering
- Construction Begins: TBD
- Construction Ends: TBD
- Total Cost: $3.7M
- Project Sponsor: Chamblee
Peachtree Boulevard Pedestrian Enhancements
A series of several small pedestrian projects to provide improvements along various intersections
- Phase: Preliminary Engineering
- Construction Begins: TBD
- Construction Ends: TBD
- Total Cost: $1.7M
- Project Sponsor: CID
East-West Railroad Crossing
Construction of a multimodal crossing over the Norfolk Southern and MARTA railroad tracks to provide better connectivity between Chamblee and Doraville
- Phase: Planning/Scoping Study
- Construction Begins: TBD
- Construction Ends: TBD
- Total Cost: TBD
- Project Sponsor: Chamblee
Shallowford Road Enhancements
Multimodal roadway improvements for a corridor connecting Buford Highway and the Doraville MARTA station
- Phase: Preliminary Engineering
- Construction Begins: TBD
- Construction Ends: TBD
- Total Cost: $3.4M
- Project Sponsor: Doraville
Regional Projects
Top End East of the I-285 Express Lanes
Construction of reversible, tolled lanes along I-285 from I-20 west to I-20 east.
- Phase: Environmental / PE
- Construction Begins: 2023
- Construction Ends: 2028
- Total Cost: $5+ Billion for total system
- Project Sponsor: GDOT
Buford Highway Arterial Rapid Transit (ART)/Bus Rapid Transit (BRT)
Launch of an Arterial Rapid Transit service to connect the Lindbergh and Doraville MARTA stations.
- Phase:
- Construction Begins: TBD
- Construction Ends: TBD
- Total Cost: TBD
- Project Sponsor: Doraville
I-285 Top End Express Lanes Transit & Trails
Construction of a high capacity premium transit within I-285 from I-75 to Tucker and a regional trail along the I-285 corridor from I-75 to Tucker.
- Phase: Planning
- Construction Begins: TBD
- Construction Ends: TBD
- Total Cost: TBD
- Project Sponsor: Top End Committee